We Have Milestones!
I spent the weekend uploading PSD files of our new site designs to our client server on Ciplex. Meanwhile, Ciplex has started to layout some milestones for web development. Screencap of milestones is below:

So here is the current plan:
.........................................................
Technical Spec
Thursday, 21 August (2 days away)
HTML and CSS Coding
Thursday, 4 September (16 days away)
Basic Drupal Installation
Thursday, 4 September (16 days away)
Start Custom Coding
Wednesday, 10 September (22 days away)
.........................................................
Tomorrow I'm meeting with Michal, our project manager, to go over everything.
Also, you may notice that I've added a Production Status area on our homepage, along with a link to some of our past and future production milestones so everyone can get a better sense of what is going on.
Looking forward to tomorrows meeting. Until then, I have to prep some spreadsheets for our accountants. I've been doing a lot of bookeeping as part of our 501(c)3 filing. Getting close!




©