We Have Milestones!

nirvan

 

I spent the weekend uploading PSD files of our new site designs to our client server on Ciplex. Meanwhile, Ciplex has started to layout some milestones for web development. Screencap of milestones is below:

screenshot of project milestones

 

So here is the current plan:

.........................................................

Technical Spec

Thursday, 21 August (2 days away)

HTML and CSS Coding

Thursday, 4 September (16 days away)

Basic Drupal Installation

Thursday, 4 September (16 days away)

Start Custom Coding

Wednesday, 10 September (22 days away)

.........................................................

Tomorrow I'm meeting with Michal, our project manager, to go over everything.

Also, you may notice that I've added a Production Status area on our homepage, along with a link to some of our past and future production milestones so everyone can get a better sense of what is going on.